Disassembly Procedure of Tunnel Boring Machine

  • Arrival1.Arrival
    2.Dismantle of manhole-side wall (Cut an opening)

    arrow

  • Maintain the Shaft3.Maintain the Shaft
    (Protect the gap between the manhole outer wall face and the outer cylinder)

    arrow

  • Disassembly and removal of the cutter4.Disassembly and removal of the cutter

    arrow

  • Disassembly and recovery of bulkhead and inner equipment5.Disassembly and recovery of bulkhead and inner equipment

    arrow

  • Push out the jacking pipe and complete the pipe construction6.Push out the jacking pipe and complete the pipe construction.